Thu, Aug 13 |
We drove up to Target and got a few things and then purchased drawer/door pulls for the bedroom cabinets.
|
|
Thu, Jul 16 |
An email from Greg suggests the bedroom cabinet doors will be finished next week.
|
|
Wed, Jun 24 |
We returned from WDW to find the bulk of the work in the bedroom had been completed. We're waiting for the cabinet fronts and doors.
|
|
Thu, May 28 |
A message from Greg, in response to my request for a sitrep, suggests the bedroom project will start in 2-3 weeks.
|
|
Tue, Mar 31 |
Greg sent an email saying Messick was behind schedule and the bedroom renovation would be postponed.
|
|
Mon, Mar 16 |
The deposit was sent for the project.
|
|
Fri, Feb 27 |
Greg sent the final proposal for the bedroom project and we agreed.
|
|
Tue, Feb 24 |
Greg came and we discussed the bedroom cabinets, making minor adjustments.
|
|
Mon, Feb 16 |
Greg called to discuss the bedroom project. We discussed the sizes of the cabinets. We’re targeting having the work done while we’re at Disney in April.
|
|
Fri, Feb 13 |
Greg sent drawings of the proposed cabinets.
|
Thu, Jan 22 |
At 1600, Greg came and we discussed the renovations Lyd wants.
Messick Brothers won’t be able to start until mid-February, at the earliest.
|
|